Main content

Town of Richmond Highway Department's Construction Updates

Posted Friday, May 19, 2023
— News

This page will display updates from the Town of Richmond Highway Department’s construction projects (not including the Rt. 2 VTrans Construction updates).

​​​​​​​​​​​​​​​​​​​​​WEEKS OF MAY 15th - MAY 22nd

​​​​​​​​​​​​​​The bulk of the Bridge St paving will be done May 19th.
​​​​​​​Line striping in the Village will occur week of May 22nd.

WEEKS OF MAY 5th -  MAY 15th

Sidewalk work on Bridge St to continue until Monday, May 15th.
Base paving in the Volunteers Green begins on Friday, May 12th, ​​​​​​​Volunteers Green traffic detour through Esplande St during paving.
​​​​​​​Bridge St milling and paving work to begin after 8 AM.
​​​​​​​Paving to follow milling as well as finished paving of Volunteers Green.

WEEKS OF APRIL 24th - MAY 5th:

Beginning Monday April 24th sidewalk replacement on the west side of Bridge Street will resume.
Expect one lane traffic during the duration of the project. 

FY23 paving will resume around May 1st on the west end of Cochran Road, north end of Dugway Road and Duxbury Road.
Expect one lane traffic for this work.