This page contains updates from VTrans on the Rt. 2 Rehabilitation Project.
More information on this project can be found on the VTrans Project Page
https://vtrans.vermont.gov/projects/US2-richmond-bolton
US-2 Rehabilitation Project
Richmond - Bolton US Route 2 Rehabilitation
DATE: September 21, 2023
TRAFFIC IMPACT: Traffic Control with one-lane of alternating travel motorists can expect moderate traffic delays during all working hours. PLEASE slow down and follow the posted speed limits.
PROJECT UPDATE: Completed installation of the second lift of pavement between Baker Street and the I-89 Exit 11 interchange. Began driveway tie-ins within the Richmond Village; Continued adjusting the sewer structures to pavement grade within the Richmond Village.
CONSTRUCTION ACTIVITIES:
The following is the anticipated work schedule for the week beginning September 24, 2023:
Sunday through Friday - 7:00 p.m. to 6:30 a.m.
-Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
-Continue ditching and shoulder work between Baker Street and the I-89 Exit 11 interchange.
Monday Through Friday - 6:30 a.m. to 6:30 p.m.
-Weather permitting, continue the final lift of paving at the eastern end of the project between Cochran Road and Lemroy Court.
-Weather permitting, continue paving the second lift of pavement from Kenyon Road to the Richmond/Williston town line.
-Continue driveway tie-ins from the eastern end of the project in Bolton to Lemroy Court.
-Continue shoulder work throughout the project limits.
PLEASE USE CAUTION AND FOLLOW THE POSTED SPEED LIMITS!
SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference US-2 Richmond, if you would like to receive weekly project updates via email.
COMPLETION DATE: July 2024
Contact Information:
Name - Stephanie Barrett - Public Information Consultant
Phone - 802-399-7847