This page contains updates from VTrans on the Richmond Bridge #29 Replacement Project
More information on this project can be found on the VTrans Project Page
https://vtrans.vermont.gov/projects/richmond-US2-bridge
RICHMOND BRIDGE BR#29
Replacement of Bridge no. 29 on US-2 in Richmond over I-89
DATE: June 26, 2025
TRAFFIC IMPACTS BELOW:
-No anticipated traffic impacts
PROJECT UPDATE: Continued with project clean-up work.
CONSTRUCTION ACTIVITIES:
The following is the anticipated work schedule for the week beginning June 30, 2025
-No work is expected as the project is shut down for the next several weeks as the contractor is working elsewhere.
PLEASE USE CAUTION WHILE TRAVELING THROUGH THE CONSTRUCTION ZONE AND FOLLOW THE POSTED SPEED LIMITS! SPEED ENFORCEMENT WILL BE PRESENT, AND FINES WILL BE DOUBLED
PROJECT TYPE: Complete bridge replacement
SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference Bridge#29, Richmond, if you would like to receive weekly project updates via email.
COMPLETION DATE: September 2025