Richmond Bridge #29 Replacement Project

Posted Thursday, December 5, 2024
News

This page contains updates from VTrans on the Richmond Bridge #29 Replacement Project
More information on this project can be found on the VTrans Project Page

https://vtrans.vermont.gov/projects/richmond-US2-bridge

RICHMOND BRIDGE BR#29
Replacement of Bridge no. 29 on US-2 in Richmond over I-89

​​​DATE:   December 5, 2024

TRAFFIC IMPACTS BELOW:
-U.S. Route 2 Monday through Friday from 6:30 a.m. to 4:00 p.m. will have traffic control present near the Richmond Fire Station allowing for intermittent stops to let trucks in/out of the project site.
-I-89 No traffic impacts.

PROJECT UPDATE:  Continued with the removal of the old U.S. Route 2 roadway on the west end of the project; Continued with project site restoration.

CONSTRUCTION ACTIVITIES:​​​​​​
The following is the anticipated work schedule for the week beginning December 9, 2024
Monday through Friday 6:30 a.m. to 4:00 p.m.:
​​​​​​​
-Continue with the removal of the old U.S. Route 2 roadway.
-Continue with extending the drainage pipes on the west end of the project.​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​
PLEASE USE CAUTION WHILE TRAVELING THROUGH THE CONSTRUCTION ZONE AND FOLLOW THE POSTED SPEED LIMITS!

PROJECT TYPE: Complete bridge replacement

SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference Bridge#29, Richmond, if you would like to receive weekly project updates via email.

COMPLETION DATE: September 2025

Contact Information:
Name - Stephanie Barrett - Public Information Consultant
Phone - 802-399-7847
Email - sbarrett@coibsinc.com