I-89 Richmond Emergency Culvert Replacement

Posted Thursday, September 22, 2022
— News

This page contains updates from VTrans on the I-89 Richmond Emergency Culvert Replacement.
More information on this project can be found on the VTrans Project Page

​DATE: September 22, 2022
TRAFFIC IMPACT: The “zipper merge” technique is in place. Motorists can expect to use both lanes until they reach the merge point, then take turns merging into the single lane of traffic, like a zipper closing.
​​CONSTRUCTION ACTIVITIES:
The following is the anticipated work schedule for the week beginning Monday, September 26, 2022. Please note the new work hours being 24 hours a day, 6 days per week.
Monday through Saturday - 24 hours per day:
Complete the “support of excavation” work.
Preparation work to begin the installation of the new culvert box culvert.
PLEASE USE CAUTION AND FOLLOW THE POSTED SPEED LIMITS!
SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference I-89 Richmond, if you would like to receive weekly project updates via email.
​​​​​​​